Starbucks Tersane Istanbul – Steel Frame
Steel frame fabrication and erection for a Starbucks store inside a historic building at Tersane Istanbul, with 265 m² of usable area. 21 tons of steel used.
- Location
- Tersane İstanbul
- Client
- Starbucks
- Area
- 265 m²
- Tonnage
- 21 t
- Started
- July 2026
- Completed
- July 2026

Steel frame fabrication and erection for a Starbucks store inside a historic stone-and-brick building with a timber roof at Tersane Istanbul. The system consists of columns, primary and secondary beams, and steel tube bracing. Columns are anchored to the floor with base plates and anchor bolts, and all connections are bolted. Members were fabricated in the workshop, primed, and erected quickly on site. The project ran from 02.07.2026 to 15.07.2026 and was completed in 14 days. With 265 m² of usable area, a total of 21 tons of steel was fabricated and erected.